BNL Sewage Treatment Plant Upgrade - P.W. Grosser Consulting, Inc.

BNL Sewage Treatment Plant Upgrade

PWGC worked closely with BNL to upgrade their sewage treatment plant in order to reduce concentrations of metals discharged into the Peconic River.

In order to comply with a New York State Department of Environmental Conservation (NYSDEC) directive to reduce concentrations of metals discharged into the Peconic River from Brookhaven National Laboratory’s (BNL) Sewage Treatment Plant (STP), the laboratory decided to upgrade the STP by adding a tertiary treatment component and re-directing the plant effluent away from the Peconic River to groundwater recharge beds.  Unique challenges to the project included the careful siting of the proposed groundwater beds so as not significantly alter the groundwater flow regime beneath the site.  Altering of the flow regime could influence the pathways of several groundwater contaminant plumes that are currently being remedied under CERCLA.  Further, the proposed groundwater recharge beds were required to be located close to the existing STP infrastructure, but not so close to the adjacent Peconic River that treated effluent would contribute base flow the river bed.  PWGC worked closely with BNL and their groundwater modeling support team to identify a location for the groundwater recharge beds that would not negatively impact the local groundwater flow regime and Peconic River base flow.

In addition to the design of the groundwater recharge beds, PWGC prepared detailed plans and specifications for the addition of a tertiary treatment system which included two drum filters and drum filter building.

PWGC’S ROLE:

  • Title I and Title II Engineering Design Services, including:
    • Performance of hydrogeologic analysis to characterize soil conditions in the
      proposed recharge area
    • Design and location of four new recharge basins
    • Evaluation of Tertiary Filtration System options
    • Design of Tertiary Filtration System
    • Design of flow monitoring station and system controls
    • Demolition Plan design and sequencing of existing discharge and monitoring equipment
    • Preparation of Construction Cost Estimates
    • Preparation of Construction Schedule using Primavera P6 software
    • Electrical design including Arc Flash and Lightning Protection analyses and standby power upgrades
  • Preparation of Title I Design Report
  • Preparation of Title II Design Package including Plans and Specifications
  • Bid Phase support services
Have a Project?
Sample Projects
Underground Injection Control Structure Cleaning & UST Closure
PWGC investigated the petroleum impact and associated anomalies at an underground storage site before closing the UST.
GTJ Tank Upgrade & Remediation Management
We excavated contaminated soil and upgraded a series of petroleum storage facilities and fueling systems to improve leak detection and spill protection.
Post-Dredging Ecological Assessment for Upper Lake
After the Upper Lake was dredged to remove invasive species, we conducted an ecological study to measure the dredging's effectiveness
green bar

Industry Updates

PWGC provides occasional industry-tailored newsletters to help you stay updated on ever-changing environmental rules, regulations, and pertinent news. Industry newsletters are published seasonally and as needed.